METCO's Relevent Experience: |
Provided Engineering Services for:
• “Design-Build” RFP Preparation including
development of project scope, general
layout and technical specifications
• Participate in round-table workshop with
proposers.
• Bid Evaluation & Contract Design
• Providing Construction Administration
Services as ‘Oversight’ Consultant
including:
• Design Build Contract Coordination
• Technical Services (Submittal Review,
RFI Response & Change Order Review)
• D/B Contractor Progress Payment
Review
• Construction Administration Services
• Quality Assurance
• Start-up and Testing Services
• Project Close-out Services
• As Needed Design Engineering Services
|
|
|
|
|
|
Design-Build Contract for Emergency Generator at Thirteen (13) DWSD Facilities
|
 |
To address Y2K program, DWSD has decided to install forty-eight (48) diesel generators at thirteen (13) locations, to be operated as emergency standby and peak shaving system.
METCO was retained to (a) prepare proposal documents for ‘Design-Build’ of this Project; and (b) provide Oversight Consulting Services during construction.
This project was on a fast track, with rigid deadline to have system on line by December 1, 1999 and must be operational to meet any emergency situation at these thirteen (13) locations on December 31, 1999.
The project was completed and the system was utilized as back-up power source on the eve of January 1, 2000.
|
|
|