In order to mitigate the current low water pressure in some of the Downriver communities during the peak summer months, DWSD proposed to construct Eleven (11) miles of transmission line starting at the intersection of I-75 and Ready Road to Sumpter Township.
METCO was tasked to perform a comprehensive Hydraulic Study to determine the size and develop the detailed Design documents for this proposed transmission line.
The Project consists of following key elements:
METCO, during the design phase had conducted the following specific tasks in developing the Construction documents:
The design phase of this Project was completed, and the construction has been temporarily deferred to incorporate the Water Master Plan recommendations for right sizing the system facilities.